Project Details

Owner
United Airlines Inc.
Location
IAH Airport Terminal C
Construction Delivery
Stipulated Lump Sum
Construction Budget
$1,420,555
Completion Date
August
2016
Size
25787 SF
United Airlines Terminal C Lobby Renovation
Renovation of United Airlines Terminal C Lobby requiring the removal of agent check-in stations at three different areas of the lobby. New podiums and scales were installed in a revised configuration at each location required new infrastructure and coordination with baggage handling systems. The existing structural art piece at the center of the lobby had to be removed to accommodate the revised layout. New finishes were required throughout the area with all work performed during off-peak airport traffic hours.